TelanganaRERA Application

General Information

Other Than Individual

Organization

FORRTUNE GREENHOMES
Partnership
No
No
No

Address Details

PLOT NO 17
TULASIS LAKSHMI NILAYAM
SANSKRUTHI TOWNSHIP
NEKNAMPUR VILLAGE
NEAR MAHALAKSHMI TEMPLE
Telangana
Ranga Reddy
Gandipet
Neknapur
500089

Organization Contact Details

Past Experience Details

Member Information

Member Name Designation Photo
SAMBIREDDY VANGA Partner View Photo
SURESH VENKATA SOMISETTY Authorized Signatory View Photo

Project Information

HMDA
GOLD CREST
On-Going Project
04/12/2020
04/12/2020
No
Residential
No

Land Details

115
185,186,187,188,189
1198.21
0
1198.21
1
1
NEIGHBOURS LAND
30 FEET ROAD
30 FEET ROAD
30 FEET ROAD

Built-Up Area Details

2683.93
296.17

Address Details

Telangana
Ranga Reddy
Gandipet
Neknapur
Near Tuljaram Temple
Neknapur
500089

Project Details

Name Proposed Booked WorkDone(In %)
Open Parking (In sqmts)
Covered Parking ( In Numbers) 25 21 80

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Supply : YES 90 WORK IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 70 WORK IN PROGRESS
Storm Water Drains : NO 0 NA
Green Strip/TOT LOT/Park : YES 10 WORK IN PROGRESS
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA
Water Conservation, Rain water Harvesting : YES 20 WORK IN PROGRESS
Energy management : YES 0 WORK IN PROGRESS
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 30 WORK IN PROGRESS
Aggregate area of recreational Open Space : YES 10 WORK IN PROGRESS

Building Details

Sr.No. Project Name Name Proposed Date of Completion (As approved by Competent Authority) Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Total Parking Area (In sqmts)
1 GOLD CREST Gold Crest 04/12/2020 00:00:00 0 0 0 6 1 596
Sr.No. Floor ID Mortgage Area Apartment Type Saleable Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 False 2BHK 85.24 1 1
2 1 False 2BHK 85.24 1 1
3 1 True 2BHK 88.73 1 1
4 1 True 3BHK 99.05 1 0
5 1 True 3BHK 108.38 1 0
6 2 False 2BHK 85.24 1 1
7 2 False 2BHK 85.24 1 1
8 2 False 2BHK 88.73 1 1
9 2 False 3BHK 99.05 1 1
10 2 False 3BHK 108.38 1 0
11 3 False 2BHK 85.24 1 1
12 3 False 2BHK 85.24 1 1
13 3 False 2BHK 88.73 1 1
14 3 False 3BHK 99.05 1 1
15 3 False 3BHK 108.38 1 1
16 4 False 2BHK 85.24 1 1
17 4 False 2BHK 85.24 1 1
18 4 False 2BHK 88.73 1 1
19 4 False 3BHK 99.05 1 1
20 4 False 3BHK 108.38 1 1
21 5 False 2BHK 85.24 1 1
22 5 False 2BHK 85.24 1 1
23 5 False 2BHK 88.73 1 1
24 5 False 3BHK 99.05 1 0
25 5 False 3BHK 108.38 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 15
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

25
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 15
11 Overall Percentage of Completion of the work done For the entire Building /Wing 46.5

Project Professional Information

Professional Name TelanganaRERA Certificate No. Professional Type
SOMA RAMANA REDDY NA Architect
KALAKOTI VIJAYA KUMAR NA Structural Engineer

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Copy of Approval Layout Plan
Proforma of the allotment letter and agreement for sale
Declaration in FORM B
Certificates of Architect (Form 4)
Certificates of CA (Form 5)
Commencement Certificate/ Building permit
Copy of Sanctioned Building Plan
GST Certificate / Details
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Copy of Proceeding Building Permission