TelanganaRERA Application

General Information

Other Than Individual

Organization

MY Home Constructions PVT. Ltd.
Company
Yes
No
No

Address Details

3
My Home Hub
biodiversity X road
Madhapur
near cyber towers
Telangana
Hyderabad
500081

Organization Contact Details

www.myhomeconstructions.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1MY HOME ABHRAResidentialNA20230OPP INOBIT MALL RAYADURGAM PAN MAKTHA SHERILINGAMPALLI MANDAL RR DIST83/1538731/03/201530/05/2015
2MY HOME ABHRAResidentialNA20230OPP INOBIT MALL RAYADURGAM PAN MAKTHA SHERILINGAMPALLI MANDAL RR DIST83/1538731/03/201530/05/2015
3MY HOME ABHRAResidentialNA20230OPP INOBIT MALL RAYADURGAM PAN MAKTHA SHERILINGAMPALLI MANDAL RR DIST83/1538731/03/201530/05/2015
4MY HOME VIHANGAResidentialNA80936.5GOPANPALLY SHARILINGAMPALLI MANDAL RR DISTRICT37/220199630/06/201709/05/2017
5MY HOME VIHANGAResidentialNA80936.5GOPANPALLY SHARILINGAMPALLI MANDAL RR DISTRICT37/220199630/06/201709/05/2017
6MY HOME VIHANGAResidentialNA80936.5GOPANPALLY SHARILINGAMPALLI MANDAL RR DISTRICT37/220199630/06/201709/05/2017

Member Information

Member Name Designation Photo
J Shyam Rao Authorized Signatory View Photo

Project Information

HMDA
MY HOME TARKSHYA
New Project
20/01/2020
31/07/2023
No
Residential
No

Land Details

147(P)
1 & 2, SITE III, GOLDEN MILE PROJECT
23554.56
0
23554.56
4
4
30m Wide Road
Neighbours Land
Neighbours Land
Neighbours Land

Built-Up Area Details

134668.11
20466.93

Address Details

Telangana
Ranga Reddy
Gandipet
Kokapet
Kokapet
500075

Project Details

Name Proposed Booked WorkDone(In %)
Open Parking (In sqmts)
Covered Parking ( In Numbers) 1388 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 InProgress
Water Supply : YES 0 Yet to be Start
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Yet to be Start
Storm Water Drains : YES 0 Yet to be Start
Green Strip/TOT LOT/Park : YES 0 Yet to be Start
Street Lighting : YES 0 Yet to be Start
Community Buildings : YES 0 Yet to be Start
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Yet to be Start
Solid Waste Management And Disposal : YES 0 Yet to be Start
Water Conservation, Rain water Harvesting : YES 0 Yet to be Start
Energy management : YES 0 Yet to be Start
Fire Protection And Fire Safety Requirements : YES 0 Yet to be Start
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Yet to be Start
Aggregate area of recreational Open Space : YES 0 Yet to be Start

Building Details

Sr.No. Project Name Name Proposed Date of Completion (As approved by Competent Authority) Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Total Parking Area (In sqmts)
1 MY HOME TARKSHYA BLOCK 1 31/07/2023 00:00:00 3 0 1 33 13060
Sr.No. Floor ID Mortgage Area Apartment Type Saleable Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 True 3 BHK 181.78 1 0
2 1 True 3 BHK 830.48 4 0
3 10 False 3 BHK 830.48 4 2
4 10 False 3 BHK 181.78 1 1
5 11 False 3 BHK 181.78 1 0
6 11 False 3 BHK 830.48 4 2
7 12 False 3 BHK 181.78 1 1
8 12 False 3 BHK 830.48 4 2
9 13 False 3 BHK 181.78 1 0
10 13 False 3 BHK 830.48 4 2
11 14 False 3 BHK 181.78 1 1
12 14 False 3 BHK 830.48 4 2
13 15 False 3 BHK 830.48 4 1
14 15 False 3 BHK 181.78 1 0
15 16 False 3 BHK 181.78 1 1
16 16 False 3 BHK 830.48 4 2
17 17 False 3 BHK 830.48 4 3
18 17 False 3 BHK 181.78 1 1
19 18 False 3 BHK 830.48 4 3
20 18 False 3 BHK 181.78 1 0
21 19 False 3 BHK 181.78 1 0
22 19 False 3 BHK 830.48 4 1
23 2 True 3 BHK 181.78 1 0
24 2 True 3 BHK 830.48 4 0
25 20 False 3 BHK 830.48 4 2
26 20 False 3 BHK 181.78 1 0
27 21 False 3 BHK 181.78 1 1
28 21 False 3 BHK 830.48 4 3
29 22 False 3 BHK 181.78 1 1
30 22 False 3 BHK 830.48 4 2
31 23 False 3 BHK 181.78 1 1
32 23 False 3 BHK 830.48 4 1
33 24 False 3 BHK 181.78 1 1
34 24 False 3 BHK 830.48 4 2
35 25 False 3 BHK 830.48 4 1
36 25 False 3 BHK 181.78 1 1
37 26 False 3 BHK 830.48 4 1
38 26 False 3 BHK 181.78 1 0
39 27 False 3 BHK 830.48 4 2
40 27 False 3 BHK 181.78 1 1
41 28 False 3 BHK 830.48 4 2
42 28 False 3 BHK 181.78 1 1
43 29 False 3 BHK 181.78 1 0
44 29 False 3 BHK 830.48 4 1
45 3 True 3 BHK 181.78 1 0
46 3 True 3 BHK 830.48 4 0
47 30 False 3 BHK 830.48 4 2
48 30 False 3 BHK 181.78 1 1
49 31 False 3 BHK 181.78 1 0
50 31 False 3 BHK 830.48 4 2
51 32 False 3 BHK 830.48 4 2
52 32 False 3 BHK 181.78 1 1
53 33 False 3 BHK 181.78 1 0
54 33 False 3 BHK 830.48 4 1
55 4 True 3 BHK 181.78 1 0
56 4 True 3 BHK 830.48 4 0
57 5 True 3 BHK 181.78 1 0
58 5 True 3 BHK 830.48 4 0
59 6 False 3 BHK 181.78 1 0
60 6 True 3 BHK 830.48 4 0
61 7 False 3 BHK 181.78 1 1
62 7 False 3 BHK 830.48 4 2
63 8 False 3 BHK 181.78 1 1
64 8 False 3 BHK 830.48 4 3
65 9 False 3 BHK 181.78 1 1
66 9 False 3 BHK 830.48 4 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 52
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 15.2
Sr.No. Project Name Name Proposed Date of Completion (As approved by Competent Authority) Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Total Parking Area (In sqmts)
2 MY HOME TARKSHYA BLOCK 2 31/07/2023 00:00:00 3 0 1 33 0 13060
Sr.No. Floor ID Mortgage Area Apartment Type Saleable Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 False 3 BHK 181.78 1 0
2 1 True 3 BHK 830.48 4 0
3 10 False 3 BHK 181.78 1 0
4 10 False 3 BHK 830.48 4 4
5 11 False 3 BHK 830.48 4 2
6 11 False 3 BHK 181.78 1 1
7 12 False 3 BHK 830.48 4 3
8 12 False 3 BHK 181.78 1 1
9 13 False 3 BHK 830.48 4 2
10 13 False 3 BHK 181.78 1 1
11 14 False 3 BHK 830.48 4 1
12 14 False 3 BHK 181.78 1 1
13 15 False 3 BHK 830.48 4 3
14 15 False 3 BHK 181.78 1 1
15 16 False 3 BHK 830.48 4 4
16 16 False 3 BHK 181.78 1 1
17 17 False 3 BHK 830.48 4 3
18 17 False 3 BHK 181.78 1 1
19 18 False 3 BHK 181.78 1 1
20 18 False 3 BHK 830.48 4 2
21 19 False 3 BHK 830.48 4 4
22 19 False 3 BHK 181.78 1 1
23 2 True 3 BHK 830.48 4 0
24 2 True 3 BHK 181.78 1 0
25 20 False 3 BHK 830.48 4 2
26 20 False 3 BHK 181.78 1 1
27 21 False 3 BHK 830.48 4 0
28 21 False 3 BHK 181.78 1 0
29 22 False 3 BHK 830.48 4 2
30 22 False 3 BHK 181.78 1 1
31 23 False 3 BHK 830.48 4 1
32 23 False 3 BHK 181.78 1 1
33 24 False 3 BHK 830.48 4 2
34 24 False 3 BHK 181.78 1 1
35 25 False 3 BHK 830.48 4 2
36 25 False 3 BHK 181.78 1 1
37 26 False 3 BHK 830.48 4 2
38 26 False 3 BHK 181.78 1 0
39 27 False 3 BHK 181.78 1 0
40 27 False 3 BHK 830.48 4 2
41 28 False 3 BHK 830.48 4 3
42 28 False 3 BHK 181.78 1 1
43 29 False 3 BHK 830.48 4 2
44 29 False 3 BHK 181.78 1 0
45 3 True 3 BHK 830.48 4 0
46 3 True 3 BHK 181.78 1 0
47 30 False 3 BHK 830.48 4 0
48 30 False 3 BHK 181.78 1 0
49 31 False 3 BHK 181.78 1 0
50 31 False 3 BHK 830.48 4 2
51 32 False 3 BHK 181.78 1 0
52 32 False 3 BHK 830.48 4 1
53 33 False 3 BHK 181.78 1 0
54 33 False 3 BHK 830.48 4 1
55 4 False 3 BHK 181.78 1 0
56 4 True 3 BHK 830.48 4 0
57 5 False 3 BHK 830.48 4 3
58 5 False 3 BHK 181.78 1 0
59 6 False 3 BHK 830.48 4 4
60 6 False 3 BHK 181.78 1 1
61 7 False 3 BHK 830.48 4 3
62 7 False 3 BHK 181.78 1 1
63 8 False 3 BHK 830.48 4 3
64 8 False 3 BHK 181.78 1 0
65 9 False 3 BHK 830.48 4 4
66 9 False 3 BHK 181.78 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 51
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 15.1
Sr.No. Project Name Name Proposed Date of Completion (As approved by Competent Authority) Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Total Parking Area (In sqmts)
3 MY HOME TARKSHYA BLOCK 3 31/07/2023 00:00:00 3 0 1 33 13060
Sr.No. Floor ID Mortgage Area Apartment Type Saleable Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 True 3 BHK 830.48 4 0
2 1 True 3 BHK 181.78 1 0
3 10 False 3 BHK 181.78 1 0
4 10 False 3 BHK 830.48 4 1
5 11 False 3 BHK 830.48 4 4
6 11 False 3 BHK 181.78 1 1
7 12 False 3 BHK 830.48 4 2
8 12 False 3 BHK 181.78 1 1
9 13 False 3 BHK 830.48 4 3
10 13 False 3 BHK 181.78 1 1
11 14 False 3 BHK 830.48 4 1
12 14 False 3 BHK 181.78 1 1
13 15 False 3 BHK 181.78 1 0
14 15 False 3 BHK 830.48 4 2
15 16 False 3 BHK 181.78 1 0
16 16 False 3 BHK 830.48 4 3
17 17 False 3 BHK 830.48 4 2
18 17 False 3 BHK 181.78 1 1
19 18 False 3 BHK 830.48 4 2
20 18 False 3 BHK 181.78 1 1
21 19 False 3 BHK 830.48 4 2
22 19 False 3 BHK 181.78 1 1
23 2 True 3 BHK 830.48 4 0
24 2 True 3 BHK 181.78 1 0
25 20 False 3 BHK 830.48 4 4
26 20 False 3 BHK 181.78 1 1
27 21 False 3 BHK 830.48 4 3
28 21 False 3 BHK 181.78 1 1
29 22 False 3 BHK 181.78 1 1
30 22 False 3 BHK 830.48 4 3
31 23 False 3 BHK 181.78 1 0
32 23 False 3 BHK 830.48 4 0
33 24 False 3 BHK 830.48 4 2
34 24 False 3 BHK 181.78 1 1
35 25 False 3 BHK 181.78 1 0
36 25 False 3 BHK 830.48 4 2
37 26 False 3 BHK 830.48 4 1
38 26 False 3 BHK 181.78 1 1
39 27 False 3 BHK 830.48 4 2
40 27 False 3 BHK 181.78 1 1
41 28 False 3 BHK 830.48 4 2
42 28 False 3 BHK 181.78 1 1
43 29 False 3 BHK 181.78 1 0
44 29 False 3 BHK 830.48 4 3
45 3 True 3 BHK 830.48 4 0
46 3 True 3 BHK 181.78 1 0
47 30 False 3 BHK 181.78 1 0
48 30 False 3 BHK 830.48 4 2
49 31 False 3 BHK 181.78 1 0
50 31 False 3 BHK 830.48 4 2
51 32 False 3 BHK 181.78 1 0
52 32 False 3 BHK 830.48 4 2
53 33 False 3 BHK 181.78 1 0
54 33 False 3 BHK 830.48 4 1
55 4 False 3 BHK 181.78 1 0
56 4 True 3 BHK 830.48 4 0
57 5 False 3 BHK 830.48 4 2
58 5 False 3 BHK 181.78 1 0
59 6 False 3 BHK 830.48 4 4
60 6 False 3 BHK 181.78 1 1
61 7 False 3 BHK 181.78 1 0
62 7 False 3 BHK 830.48 4 1
63 8 False 3 BHK 830.48 4 3
64 8 False 3 BHK 181.78 1 1
65 9 False 3 BHK 830.48 4 3
66 9 False 3 BHK 181.78 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 45
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 14.5
Sr.No. Project Name Name Proposed Date of Completion (As approved by Competent Authority) Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Total Parking Area (In sqmts)
4 MY HOME TARKSHYA BLOCK 4 31/07/2023 00:00:00 3 0 1 33 0 13060
Sr.No. Floor ID Mortgage Area Apartment Type Saleable Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 True 3 BHK 830.48 4 0
2 1 True 3 BHK 181.78 1 0
3 10 False 3 BHK 830.48 4 3
4 10 False 3 BHK 181.78 1 1
5 11 False 3 BHK 830.48 4 3
6 11 False 3 BHK 181.78 1 1
7 12 False 3 BHK 830.48 4 2
8 12 False 3 BHK 181.78 1 1
9 13 False 3 BHK 830.48 4 2
10 13 False 3 BHK 181.78 1 1
11 14 False 3 BHK 830.48 4 3
12 14 False 3 BHK 181.78 1 1
13 15 False 3 BHK 830.48 4 2
14 15 False 3 BHK 181.78 1 1
15 16 False 3 BHK 181.78 1 1
16 16 False 3 BHK 830.48 4 3
17 17 False 3 BHK 830.48 4 3
18 17 False 3 BHK 181.78 1 1
19 18 False 3 BHK 830.48 4 2
20 18 False 3 BHK 181.78 1 1
21 19 False 3 BHK 830.48 4 2
22 19 False 3 BHK 181.78 1 1
23 2 True 3 BHK 830.48 4 0
24 2 True 3 BHK 181.78 1 0
25 20 False 3 BHK 181.78 1 1
26 20 False 3 BHK 830.48 4 3
27 21 False 3 BHK 830.48 4 1
28 21 False 3 BHK 181.78 1 1
29 22 False 3 BHK 830.48 4 4
30 22 False 3 BHK 181.78 1 1
31 23 False 3 BHK 830.48 4 4
32 23 False 3 BHK 181.78 1 1
33 24 False 3 BHK 830.48 4 2
34 24 False 3 BHK 181.78 1 1
35 25 False 3 BHK 181.78 1 1
36 25 False 3 BHK 830.48 4 2
37 26 False 3 BHK 181.78 1 1
38 26 False 3 BHK 830.48 4 3
39 27 False 3 BHK 830.48 4 4
40 27 False 3 BHK 181.78 1 1
41 28 False 3 BHK 181.78 1 0
42 28 False 3 BHK 830.48 4 2
43 29 False 3 BHK 830.48 4 4
44 29 False 3 BHK 181.78 1 1
45 3 True 3 BHK 830.48 4 0
46 3 True 3 BHK 181.78 1 0
47 30 False 3 BHK 830.48 4 3
48 30 False 3 BHK 181.78 1 1
49 31 False 3 BHK 830.48 4 3
50 31 False 3 BHK 181.78 1 1
51 32 False 3 BHK 181.78 1 0
52 32 False 3 BHK 830.48 4 3
53 33 False 3 BHK 181.78 1 0
54 33 False 3 BHK 830.48 4 2
55 4 True 3 BHK 181.78 1 0
56 4 True 3 BHK 830.48 4 0
57 5 True 3 BHK 830.48 4 0
58 5 True 3 BHK 181.78 1 0
59 6 True 3 BHK 830.48 4 0
60 6 True 3 BHK 181.78 1 0
61 7 True 3 BHK 830.48 4 0
62 7 True 3 BHK 181.78 1 0
63 8 False 3 BHK 830.48 4 2
64 8 False 3 BHK 181.78 1 1
65 9 False 3 BHK 181.78 1 1
66 9 False 3 BHK 830.48 4 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 46
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 14.6

Project Professional Information

Professional Name TelanganaRERA Certificate No. Professional Type
MY HOME CONSTRUCTIONS PVT., LTD., NA Contractor
T. VISHNU VARDHAN NA Architect
SRINIVASA RAO BOLIMUNTA NA Structural Engineer

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Approval Layout Plan
Copy of Approval Layout Plan
Proforma of the allotment letter and agreement for sale
Declaration in FORM B
Certificates of Architect (Form 4)
Certificates of CA (Form 5)
Commencement Certificate/Copy of Building Permit/Proceedings
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
Copy of Sanctioned Building Plan
GST Certificate / Details
GST Certificate / Details
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Copy of Proceeding Building Permission