TelanganaRERA Application

General Information

Other Than Individual

Organization

Primark Developers
Partnership
Yes
No
No

Address Details

Flat no 102
Primark Anithas Ashwini Apartment
Raghavendra Nagar
Kondapur
Near Gem Service centre
Telangana
Ranga Reddy
Serilingampally
500084

Organization Contact Details

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Primark SreenidhiResidentialNA748.26 Plot No.260261 C262 C Raghavendra Nagar colony Kondapur Hyderabad-500084260, 261 C, 262 C11501/05/202301/10/2018
2Primark SreenidhiResidentialNA748.26 Plot No.260261 C262 C Raghavendra Nagar colony Kondapur Hyderabad-500084260, 261 C, 262 C11501/05/202301/10/2018

Member Information

Member Name Designation Photo
Sambasivarao Borra Authorized Signatory View Photo

Project Information

GHMC
2/C11/03837/2018
Sree Prasads Abode
On-Going Project
04/03/2024
04/03/2024
No
Residential
Yes

Land Details

85,86,87 & 88 PART
1816 & 1817
501.42
0
501.42
1
1
30 feet wide road
Plot No 1826 and 1827
Plot no 1815
Plot No 1818

Built-Up Area Details

1143.80
118.08

Address Details

Telangana
Ranga Reddy
Serilingampally
Raghavendra Colony
JD homes road
Kondapur
500084

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement Office Number Other Details
Sree Prasads Abode GVBS Murthy and Chappidi Anil Kumar Individual AreaShare NA Primark Anithas Ashwini

Project Details

Name Proposed Booked WorkDone(In %)
Open Parking (In sqmts)
Covered Parking ( In Numbers) 10 0 42

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Supply : YES 50 work in process
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 50 work in process
Storm Water Drains : YES 50 work in process
Green Strip/TOT LOT/Park : YES 50 work in process
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 50 work in process
Water Conservation, Rain water Harvesting : YES 50 Water Supply arranged
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 work in process
Aggregate area of recreational Open Space : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion (As approved by Competent Authority) Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Total Parking Area (In sqmts)
1 Sree Prasads Abode Sree prasads Abode 04/03/2018 00:00:00 6 1 229
Sr.No. Floor ID Mortgage Area Apartment Type Saleable Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 True 3 BHK 139.8 1 0
2 1 True 3 BHK 144.4 1 0
3 2 False 3 BHK 139.8 1 0
4 2 False 3 BHK 144.4 1 0
5 3 False 3 BHK 139.8 1 0
6 3 False 3 BHK 144.4 1 0
7 4 False 3 BHK 139.8 1 0
8 4 False 3 BHK 144.4 1 0
9 5 False 3 BHK 139.8 1 0
10 5 False 3 BHK 144.4 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

20
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 25
11 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5

Project Professional Information

Professional Name TelanganaRERA Certificate No. Professional Type
Srilatha NA Architect
kv apparao NA Structural Engineer

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Copy of Approval Layout Plan
Copy of Approval Layout Plan
Copy of Approval Layout Plan
Copy of Approval Layout Plan
Proforma of the allotment letter and agreement for sale
Declaration in FORM B
Certificates of Architect (Form 4)
Certificates of CA (Form 5)
Commencement Certificate/ Building permit
Copy of Sanctioned Building Plan
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Copy of Proceeding Building Permission