Sr.No. |
Project Name
|
Name
|
Proposed Date of Completion (As approved by Competent Authority)
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Total Parking Area (In sqmts)
|
1 |
RAJAPUSHPA ETERNA
|
ELAN BLOCK A
|
31/12/2021 00:00:00
|
2
|
1
|
1
|
15
|
0 |
|
0 |
|
|
Sr.No.
|
Floor ID
|
Mortgage Area
|
Apartment Type
|
Saleable Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 |
True |
3BHK |
1741 |
8 |
0 |
2 |
10 |
False |
3BHK |
1872.9 |
8 |
5 |
3 |
11 |
False |
3BHK |
1872.9 |
8 |
4 |
4 |
12 |
False |
3BHK |
1872.9 |
8 |
6 |
5 |
13 |
False |
3BHK |
1872.9 |
8 |
5 |
6 |
14 |
False |
3BHK |
1872.9 |
8 |
5 |
7 |
15 |
False |
3BHK |
1872.9 |
8 |
5 |
8 |
2 |
True |
3BHK |
1741 |
8 |
0 |
9 |
3 |
False |
3BHK |
1872.9 |
8 |
2 |
10 |
4 |
False |
3BHK |
1872.9 |
8 |
5 |
11 |
5 |
False |
3BHK |
1872.9 |
8 |
3 |
12 |
6 |
False |
3BHK |
1872.9 |
8 |
4 |
13 |
7 |
False |
3BHK |
1872.9 |
8 |
5 |
14 |
8 |
False |
3BHK |
1872.9 |
8 |
5 |
15 |
9 |
False |
3BHK |
1872.9 |
8 |
5 |
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|
Sr.No. |
Project Name
|
Name
|
Proposed Date of Completion (As approved by Competent Authority)
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Total Parking Area (In sqmts)
|
2 |
RAJAPUSHPA ETERNA
|
TIARA BLOCK B
|
31/12/2021 00:00:00
|
2
|
1
|
1
|
13
|
|
|
0 |
|
|
Sr.No.
|
Floor ID
|
Mortgage Area
|
Apartment Type
|
Saleable Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 |
True |
4BHK |
752.5 |
2 |
0 |
2 |
10 |
False |
4BHK |
1605.3 |
4 |
0 |
3 |
11 |
False |
4BHK |
1605.3 |
4 |
3 |
4 |
12 |
False |
4BHK |
1605.3 |
4 |
0 |
5 |
13 |
False |
4BHK |
1605.3 |
4 |
0 |
6 |
2 |
True |
4BHK |
1505 |
4 |
0 |
7 |
3 |
False |
4BHK |
1605.3 |
4 |
2 |
8 |
4 |
False |
4BHK |
1605.3 |
4 |
0 |
9 |
5 |
False |
4BHK |
1605.3 |
4 |
1 |
10 |
6 |
False |
4BHK |
1605.3 |
4 |
2 |
11 |
7 |
False |
4BHK |
1605.3 |
4 |
2 |
12 |
8 |
False |
4BHK |
1605.3 |
4 |
2 |
13 |
9 |
False |
4BHK |
1605.3 |
4 |
0 |
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|
Sr.No. |
Project Name
|
Name
|
Proposed Date of Completion (As approved by Competent Authority)
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Total Parking Area (In sqmts)
|
3 |
RAJAPUSHPA ETERNA
|
PANACHE BLOCK C
|
31/12/2021 00:00:00
|
2
|
1
|
1
|
15
|
|
|
0 |
|
|
Sr.No.
|
Floor ID
|
Mortgage Area
|
Apartment Type
|
Saleable Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 |
True |
3BHK |
1741 |
8 |
0 |
2 |
10 |
False |
3BHK |
1872.9 |
8 |
4 |
3 |
11 |
False |
3BHK |
1872.9 |
8 |
6 |
4 |
12 |
False |
3BHK |
1872.9 |
8 |
4 |
5 |
13 |
False |
3BHK |
1872.9 |
8 |
5 |
6 |
14 |
False |
3BHK |
1872.9 |
8 |
5 |
7 |
15 |
False |
3BHK |
1872.9 |
8 |
5 |
8 |
2 |
False |
3BHK |
1741 |
8 |
2 |
9 |
3 |
False |
3BHK |
1872.9 |
8 |
4 |
10 |
4 |
False |
3BHK |
1872.9 |
8 |
5 |
11 |
5 |
False |
3BHK |
1872.9 |
8 |
5 |
12 |
6 |
False |
3BHK |
1872.9 |
8 |
4 |
13 |
7 |
False |
3BHK |
1872.9 |
8 |
6 |
14 |
8 |
False |
3BHK |
1872.9 |
8 |
5 |
15 |
9 |
False |
3BHK |
1872.9 |
8 |
5 |
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|
Sr.No. |
Project Name
|
Name
|
Proposed Date of Completion (As approved by Competent Authority)
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Total Parking Area (In sqmts)
|
4 |
RAJAPUSHPA ETERNA
|
CLUBHOUSE
|
31/12/2021 00:00:00
|
2
|
1
|
1
|
5
|
|
|
0 |
|
|
Sr.No.
|
Floor ID
|
Mortgage Area
|
Apartment Type
|
Saleable Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 |
False |
AMENITIES |
0 |
0 |
0 |
2 |
2 |
False |
AMENITIES |
0 |
0 |
0 |
3 |
3 |
False |
AMENITIES |
0 |
0 |
0 |
4 |
4 |
False |
AMENITIES |
0 |
0 |
0 |
5 |
5 |
False |
AMENITIES |
0 |
0 |
0 |
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
100
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
100
|
|